Gold Ore Processing Plant
At the Processing Plant, gold and silver are extracted from the ore. The processing plant alternates between treating ore from the Martha Mine open pit and from the Favona underground mine.
Gold ore processing consists of the following stages:
crushing and grinding of the ore
I.addition of process water (generally decanted from the tailings pond) to form a slurry
II.addition of lime to the ore, and cyanide solution to the slurry, to leach the gold and silver into solution
III.addition of carbon to adsorb dissolved metals and remove them from the slurry
IV.stripping the metals from the carbon by acid washing and circulation of a caustic cyanide solution
V.precipitation of the gold and silver by electro-winning
VI.smelting of metal products into bars of dor?? bullion
VII.pumping of the barren slurry (tailings) to the tailings storage facility.
VIII.The Processing Plant has the capacity to treat up to 1.25 million tonnes per annum of ore. Get ball mill,Mineral Processing,beneficiation From http://www.ballmill8.com
Gold Ore Processing Plant
At the Processing Plant, gold and silver are extracted from the ore. The processing plant alternates between treating ore from the Martha Mine open pit and from the Favona underground mine.
Gold ore processing consists of the following stages:
crushing and grinding of the ore
I.addition of process water (generally decanted from the tailings pond) to form a slurry
II.addition of lime to the ore, and cyanide solution to the slurry, to leach the gold and silver into solution
III.addition of carbon to adsorb dissolved metals and remove them from the slurry
IV.stripping the metals from the carbon by acid washing and circulation of a caustic cyanide solution
V.precipitation of the gold and silver by electro-winning
VI.smelting of metal products into bars of dor?? bullion
VII.pumping of the barren slurry (tailings) to the tailings storage facility.
VIII.The Processing Plant has the capacity to treat up to 1.25 million tonnes per annum of ore. Get ball mill,Mineral Processing,beneficiation From http://www.ballmill8.com
Click for Details --> http://www.ballmill8.com <--
|
|
 |

|
|
LinkedIn Recommendation:
Eura Unrath - Scientific Photographer at Roboto Industries - Teo wrote my business plan and found some revenue models I hadn't considered. I am looking forward to working with Teo on some of the things in the plan. Great work. Great at finding potential problems and working through to the best answer. I had a good time working with him too. If you need a business plan, Teo does a great job! - March 17, 2012, Eura was Teo's client |
|